top of page
Search

Bogura 20 MW (Energy Prima) DFG Power Plant

Updated: Oct 16, 2023

Current Status: Expired

Figure: Bogura 20 MW DFG Power plant; Source: Google Maps


Bogura 20 MW Gas Power Plant, also known as Energy Prima Bogura Rental Power Plant, is a reciprocating engine-based power plant situated in the PDB compound under Bogura Sadar Upazila in Bogura District of Bangladesh (Location: 24.8414, 89.3528). It is sponsored by Energy Prima Limited (EPL), a subsidiary of Hosaf Group, as a Rental Power Plant (RPP) for three years. The sponsor declared its Commercial Operation Date (COD) on 13 June 2011, and, as per schedule, it is to retire on 12 June 2014. However, the power plant will be phased out on 12 November 2024 after 13 years of operation.


Capacity

The installed (gross) and derated (net) capacity of the power plant is 26.5 MW and 20 MW, respectively.


Context

Energy Prima's Bogura 20 MW rental power plant was one of five expensive rental power plants that the Power Development Board signed deals with a couple of companies to install in 2008 (Newsprojects, 2008). However, due to a lack of required equipment, power generation from the power plant was uncertain (Hasibur 2009). On 20 February 2010, Chairman of Energy Prima Ltd Moazzam Hossain claimed that the plant was yet to start generating power due to a shortage of equipment. Still, it was ready to generate and supply 14 MW of power to the national grid as per the proposal (Hasibur 2010).

On April 8, 2015, the company obtained approval from the Cabinet Purchase Committee to renew its power purchase agreements with the government for a third time. Lastly, on 29 Dec 2021, at the 42nd meeting of the CCGP with Finance Minister AHM Mustafa Kamal, the 20 MW gas-based rental power plant in Bogura district has also been extended for three more years (Jagonews 2021).


Land Acquisition

The power plant occupies a 1.21-acre plot of land. (Google Earth)


Finance

National Credit and Commerce (NCC) Bank Ltd financed the power plant.


Sponsors

The power plant was sponsored by Energy Prima Limited (EPL), a sister concern of Hosaf Group, as a Rental Power Plant.


Contractors

Insufficient information


Fuel Supply

BPDB completed work of the gas line under the supervision of PGCL at a cost of Tk 3.18 crore in November to ensure gas supply for this power plant (Hasibur 2009).


Power generation

According to the PPA, BPDB is to purchase electricity from the power plant at a rate of 3.6 cents per unit (kWh) (Newsprojects, 2008). It could generate 27.88 million units (GWh) of electricity at a 15.9% plant load factor (PLF). The PPA time was further extended by the Cabinet Committee on Government Purchase (CCGP) for a further three years, ending in November 2024, at BDT 2.03 per kWh. For the next three years, BPDB will spend a total of BDT 54 crore, or about BDT 18 crore, to purchase electricity from the power plant (Mehedi H., 2022).


Capacity charge

BPDB had to pay USD 488,386.09 (BDT 5.35 crore when USD 1=BDT 109.75) in FY 2020-2021 to the sponsor as the capacity charge per day.

Environment

According to Section 12 of the Bangladesh Environment Protection Act 1995, Environmental Impact Assessment (EIA) is obligatory for any industry (MOLJPA 1995). Polluting industries, such as power plants, must undergo an Initial Environmental Examination (IEE) and EIA as directed in the Environmental Conservation Rules 2017 (MOEFCC 1997). But, to date, no IEE or EIA report has been conducted for the power plant.


References


71 views
bottom of page