Current Status: Construction
Source: (FFS, 2023)
Ghorashal 410 MW (BPDB) DFG Power Plant (Unit 3), also known as Ghorashal Power Station (Unit-3) or Ghorashal Repowered CC Power Plant Unit-3, is a Combined Cycle (CC) power plant situated in Ghorashal under Palash Upazila in Narsingdi District of Bangladesh (Location: 23.9801, 90.6371). The Bangladesh Power Development Board (BPDB) has sponsored it as a State-owned Power Plant (SOPP) for 25 years. The power plant started commercial operation with an installed capacity of 210 MW on 14 September 1986, and, as per the schedule, it is to retire on 13 September 2011. In June 2016, BPDB got approval to increase its capacity from 210 MW to 409 MW. The required Commercial Operation Dates (COD) were 30 April 2018 (Gas Turbine unit) and 30 April 2019 (Steam Turbine unit). However, the dates for both units have been delayed to 30 April 2023 (BPDB 2022). Still, in 2024 the Ghorashal Repowering Stations Units 3 and 4 are under construction. 97 percent and 95 percent of the units are complete accordingly according to the progress report of PDB (TDS 2024).
Capacity
The installed (gross) capacity of the power plant is 400 MW±5%.
Context
The Bangladesh Power Development Board (BPDP) has taken several actions to increase power generation based on the recommendation of the Power System Master Plan 2010 (PSPM 2010). One such action is to enhance power generation by consuming slightly more fuel (gas) by repowering the existing old Steam power plants to combined cycle power plants. This project aims to retrofit the existing steam turbine and its auxiliaries at Ghorashal, Palash, and Narsingdi, and repower the existing 210 MW third unit to 400 MW±5% CCPP. This has been accomplished by installing one gas turbine unit and one heat recovery steam generator (HRSG).
The planned construction site is roughly 17 acres (6.88 hectares) of BPDB's fallow land on the northern side, close to unit 3 and inside the Ghorashal power plant's perimeter. The location of the site is on the northern side of "Parulia Morr (Issakhali)-Ghorashal Zila Road" and on the eastern bank of the Shitalakshya River. The site is situated in Palash Mauza, Ghorashal Municipality, which is part of Palash Upazila, Narsingdi district, administratively. The proposed power plant will receive its natural gas supply from Petrobangla's current allocation to the Ghorashal Power Plant via Units 3 and 4's current regulating and metering station (RMS) (MIGA, 2014).
Land Acquisition
Approximately 17 acres (6.88 ha) of land was allocated for the construction of the proposed power plant. (MIGA, 2014).
Finance
To finance up to US$ 200 million in debt financing and USD$ 50 million in swap transactions over 13 years, the Hong Kong Shanghai Bank Corporation Limited (HSBC) of Hong Kong, China, has asked MIGA to grant the Ghorashal Unit 3 Repowering project in Bangladesh a Non-Honoring of Sovereign Financial Obligation guarantee. (MIGA, 2023).
Sponsor
The power plant has been sponsored by the Bangladesh Power Development Board (BPDB) as a State-owned Power Plant (SOPP) for 25 years (BPDB 2022).
Contractors
The construction of the Project will be handled by an Engineering, Procurement, and Construction contractor that is a joint venture between China National Machinery Import & Export Corporation (CMC) and Alstom Switzerland Ltd. Baden ("Alstom"). The consortium's technical leader, Alstom, will supply essential equipment such as gas turbines, HRSG, and retrofitting of steam turbines under the terms of the EPC contract, while CMC will lead the consortium and handle overall project management. The real construction will be handled by First Northeast Electric Power Engineering Company, a construction subcontractor that CMC has hired. The primary equipment for the Project will be provided by Alstom (MIGA, 2023).
Fuel Supply
The fuel used in this power plant is natural methane gas (CH4). The supplier of the gas is Titas Gas Transmission Company (Hasan M., 2023).
Power Generation
The project also entails building Unit 3's civil structures and a 230kV switchyard. A proposed 28 km, 230 kV transmission line that would connect the power complex to Tongi, about 15 km north of Dhaka, will be used to evacuate the power produced by the project (SERV, 2023). BPDB received permission in June 2016 to expand unit three's current capacity from 210 MW to 409 MW. For the gas turbine unit, the required Commercial Operation Dates (COD) were April 30, 2018; for the steam turbine unit, they were April 30, 2019. The dates for both units, however, have been moved to April 30, 2023 (BPDB 2022).
Environment
The Center for Environmental and Geographic Information Services (CEGIS) conducted an initial environmental examination (IEE) in October 2013 regarding the re-powering of Ghorasal's existing third unit. Environmental Impact Assessment (EIA) of Regent Energy and Power Ltd. at Ghorashal, Palash, Narsingdi by Adriot Environment Consultants Ltd. (AECL) dated October 2013; Environmental Impact Assessment (EIA) of Re-Powering of Ghorasal existing 3rd Unit by CEGIS dated June 2014 (SERV, 2023).
According to MIGA's 2013 Policy on Environmental and Social Sustainability, the proposed repowering of Unit 3 at the Ghorashal power complex falls under Category A. Water abstraction and effluent discharge, air pollution (NOx and greenhouse gases), noise, the generation and disposal of solid and hazardous waste (including asbestos), and risks to the health and safety of workers and the community are the main potential environmental and social issues related to the project. The majority of these effects can be controlled by following widely accepted performance standards, guidelines, and/or design criteria (MIGA, 2023).
Carbon footprints
Emissions are predicted to be about 360 tons of CO2 per gigawatt-hour (GWh). The project's annual CO2 emissions are predicted to be 1.31 million tons of CO2 equivalent when operating at full capacity (MIGA, 2014).
Criticism
Coal and gas are the main sources of fuel used to boil water in the Ghorashal Power Station (GPS). Water is primarily supplied by the Shitalakshya River. After using it, it releases water into the river once more (Hasan M., 2023). Power generation projects are categorized as "Red Category" by the Bangladesh Department of Environment (DoE). To obtain Site Clearance and Environmental Clearance Certificates, Red Category projects must prepare and submit an Initial Environmental Examination (IEE) and an Environmental Impact Assessment (EIA) to the Department of Environmental Protection (DoE). In October 2013, an IEE with a comprehensive Terms of Reference (TOR) for the EIA study was submitted to DoE. In February 2014, an Environmental Impact Assessment (EIA) was prepared and submitted to BPDB (SERV, 2023).
References
BPDB (2022). Power Sector Progress Report. Bangladesh Power Development Board: 15 June, 2022
FFS (2023). “Ghorashal 3 - Bangladesh”. Flenco Fluid System (FFS): 30 November, 2023.
Hasan M. (2023). ”Ghorashal Power Station (GPS) Information” BD Electricity: January 20, 2023.
MIGA (2014). “Environmental Impact Assessment (EIA) of Re-Powering of Ghorashal Existing 3rd Unit With Gas Based Combined Cycle”. Multilateral Investment Guarantee Agency (MIGA): June 2014.
MIGA (2023). “Ghorashal 3rd Unit Repowering Project”. Multilateral Investment Guarantee Agency (MIGA): 30 November 2023.
SERV (2023). “Environmental and Social Review Summary Ghorasal Unit 3 Re-Powering Project”. Swiss Export Risk Insurance (SERV): 30 November 2023.
TDS (2024). “Amid gas crisis, 2 gas-run power plants firing up” The Daily Star (TDS): 1 February 2024