Lalmonirhat 30 MW (Intraco) Solar Power Plant
- Jun 25
- 6 min read
Current Status: Operation

Source: (DB 2023)
Lalmonirhat 30 MW Solar Power Plant, also known as Intraco Lalmonirhat Solar Park, is a solar Photovoltaic (PV) power plant situated in Dakshin Bhotmarir Char of Bhotmari Union under Kaliganj Upazila in Lalmonirhat District of Bangladesh (Coordinates: 25.9978, 89.1524). It is sponsored by Intraco Solar Power Limited (ISPL), a Joint Venture Company (JVC) of Paramount Group, as a private Independent Power Producer (IPP) for 20 years. The power plant started its test run on 23 August 2022 and commercial operation on 28 August 2022. As per schedule, it will retire on 27 August 2042.
Capacity
The installed (gross) and derated (net) capacity of the power plant is 43 MW and 30 MW, respectively.
Context
On 27 August 2017, Intraco Solar Power Ltd (ISPL) finalised deals with two government entities to establish a solar power facility and deliver 30 megawatts of electricity to the national power grid (DS 2017).The power plant belongs to Intraco Solar Power Ltd. (ISPL), an associate company of Paramount Textile Ltd. (PTL), a publicly listed company primarily engaged in textile manufacturing. PTL has recently expanded its investment scope by diversifying its portfolio.
Intraco Solar Power Limited purchased about 300 acres of land in Gangachara Upazila for the project during that period. But unfortunately the entire land was lost in the river due to the erosion of the Teesta. Later, when Intraco Solar Power Limited applied to the government to change the location of the project in 2018, a high-level delegation of the government inspected the site and approved the current location of the project in Shaulmari village of Kaliganj upazila of Lalmonirhat district (AS 2021). After that intraco solar power limited project area land use trade licence from the local union council and no objection for land use and power station approval was obtained from the office of the district commissioner (PVM 2022).
According to the Power Purchase Agreement (PPA) signed on 27 August 2017, the power plant's Commercial Operation Date (COD) was scheduled as 26 June 2022. But it has been delayed and rescheduled to 26 August 2022. The government has agreed to purchase electricity under the condition of "no electricity no payment basis" spanning a period of up to 20 years, at a rate of $0.16 per kilowatt-hour. In an effort to fulfil its social responsibility within the project vicinity, Intraco Solar Power Limited extends power lines to serve the local public and supplies electricity to select households. Moreover, within the project area, the company constructs a 1.70-kilometer road to facilitate movement for hundreds of thousands of students and around 15 thousand marginalized individuals living in remote grasslands.
Construction that commenced in 2020 is scheduled for completion by 2022. Social Welfare Minister Nuruzzaman Ahmed officially inaugurated the solar power plant on August 28 of that same year. Following the inauguration, Intraco Solar has consistently supplied uninterrupted power. Prior to this project, Intraco initiated the establishment of a plant in the Gangachara upazila of Rangpur. However, due to flood and river erosion, the initially chosen char (riverine island) faced damage during that period. Consequently, Intraco opted for the Shaulmari char in Kaliganj as an alternative location. The plant was initiated on a total area of 115.02 acres, comprising 52.02 acres of government land and an additional 63 acres acquired from different private landowners. Throughout this period, Intraco undertook various initiatives, including river management efforts. They also developed essential infrastructure, such as constructing roads and buildings, within the designated area.
Land Acquisition
The total reported land area of the power plant varies across different sources. Approximately 63 acres refer only to privately acquired land, while project documents indicate a total area of about 115.02 acres, including 52.02 acres of government land and 63 acres of private land acquisition. PV Magazine (2022) reports a coverage of around 110 acres (PVM, 2022). In contrast, the project developer has claimed an area of approximately 120 acres, whereas local residents allege that up to 200 acres of land may have been enclosed within the project boundary. These variations highlight inconsistencies among official records, developer statements, and local perceptions regarding the actual extent of land acquisition.
Finance
Funding for the project was planned to be sourced from Infrastructure Development Company Limited (IDCOL), a government-owned non-bank financial institution established by the Government of Bangladesh in 1997, along with contributions from local banks (DS, 2017). Later, Paramount BTrac Energy Limited (PBEL) acquired an 80% stake in the project for approximately BDT 60 crore (TBS, 2020). According to PV Magazine (2022), the total investment in the project was estimated at USD 55 million, and the company expected annual revenue of around USD 9 million from the power plant (PVM, 2022).
Sponsor
The project is sponsored by Intraco Solar Power Limited (ISPL). In 2020, Paramount Textile Limited (PTL) acquired an 80% stake in ISPL from Intraco CNG Limited for approximately BDT 60 crore (TDS, 2020; TBS, 2022). Following the acquisition, PTL became the majority shareholder of the project company and played a key role in the development and implementation of the solar power plant.
Contractor
Paramount Textile Limited (PTL) purchased an 80% share of Intraco Solar Power Limited (ISPL), thereby becoming the majority shareholder of the solar power project (TBS, 2022).
Environment
According to Section 12 of the Bangladesh Environment Protection Act 1995, Environmental Impact Assessment (EIA) is obligatory for any industry (MOLJPA, 1995). The polluting industries, such as power plants, have to go through an Initial Environmental Examination (IEE) and EIA as directed in the Environmental Conservation Rules 1997 (MOEFCC, 1997). But unfortunately, no Environmental Impact Assessment (EIA) report was found.
Though this power plant will emit low carbon, there has been a lot of news that the construction of this power plant damaged the environment a lot. Many agricultural lands have been destroyed to establish this power plant. A two kilometre long and 50 feet wide road is being constructed along the banks of the river for transportation that may damage the water flow of the river. According to the environmental conservation rule 2023 the project falls in the “Yellow” indicating it as a slightly harmful project for the environment (MOEFCC 2023).
Criticism
Intraco Solar is facing allegations of encroaching on farmers' land and causing detrimental effects to the Teesta river. Their solar power project involves constructing a 50-feet wide and two-kilometre long road along the riverbanks. The unregulated construction of this road has nearly blocked the left bank channel of the Teesta. According to the Water Development Board, this unplanned road development will result in resource depletion, including increased river erosion. River experts have labelled this as 'Teesta's devastation' and have urgently demanded an immediate halt to these activities. The people of the village have been cultivating that pasture across the river for generations. But suddenly their land was surrounded by barbed wire. They have not even one percent of land left for cultivation.The construction of the road within the Bamti channel for the solar power project will create blockages in the water flow, leading to significant disruptions. This obstruction is anticipated to result in widespread damage across different areas, notably impacting the right bank of the region. Local residents along the Teesta riverbank in Gangachara warned that rising water pressure was affecting roads and embankments due to solar panel installations, and that thousands of homesteads and agricultural lands could be lost to the river (DT, 2025).
Reference
AS (2021).”লালমনিরহাটে ইন্ট্রাকো সোলার পাওয়ার লিমিটেড স্থাপন হলে হাজারও লোকের কর্মসংস্থান হবে”. Amar Shongbad. 16 August 2021
DS (2017). “Intraco to set up 30 MW solar power plant”. The Daily Star . 28 August 2017.
DT (2025). “Over 40,000 stranded in 5 districts as Teesta flows above danger mark”. Dhaka Tribune (DT): 14 August 2025
PVM (2022). “Bangladesh switches on 30 MW of solar”. PV Magazine . 1 September 2022.
TBS (2020). “Paramount Textile now investing in renewable energy”. The Business Standard (TBS): 16 November, 2020
TBS (2022). “Power plant of Paramount Textile’s subsidiary starts commercial operation”. The Business Standard (TBS): 28 August 2022
TDS (2020). “Paramount Textile to buy 80pc stake in Intraco Solar for Tk 60cr”. The Daily Star (TDS): 16 November 2020
MOEFCC (1997). “The Environment Conservation Rules, 1997” The Environment Conservation Rules: 27 August, 1997.
MOEFCC (2023). “The Environmental Conservation Rules”. Ministry of Environment, Forest and Climate Change (MOEFCC): 5 March 2023.
MOLJPA (1995). “Bangladesh Environment Conservation Act 1995”. Legislative and Parliamentary Affairs Division, Ministry of Law, Justice and Parliamentary Affairs (MOLJPA): 16 February 1995.
