Current Status: Operation
Rupsha 105 MW Furnace Oil Power Plant, also known as Orion Rupsha Power Plant, is a reciprocating engine-based power plant situated in Jabusha under Rupsha Upazila in Khulna District of Bangladesh (Location: 22.7671, 89.5848). It is sponsored by Orion Power Rupsha Limited (OPRL), a subsidiary of Orion Group, as a private Independent Power Producer (IPP) for 15 years. OPRL declared its Commercial Operation Date (COD) on 14 October 2018 and, as per schedule, the power plant is to retire on 13 October 2033.
Capacity
The installed (gross) and derated (net) capacity of the power plant is 110.67 MW and 105 MW respectively.