top of page

Patuakhali Thermal Power Plant starts trial production

Jan 19, 2025

BSS

PATUAKHALI, Jan 19, 2025 (BSS) - Patuakhali 1320 MW Thermal Power Plant hasstarted its trial production.

 

The entire 660 MW of electricity of the first unit will besupplied to the national grid in phases, said Engineer Ashraf Uddin,supervisor of Patuakhali 1320 MW Thermal Power Plant, today.

 

Work is going on in full swing to start production activities of the secondunit (660 MW) in the next March, he added.

 

The authorities started production activities of the first unit (660 MW)around 12 midnight on Saturday.

 

Currently, 110 MW of electricity generated by this plant is being supplied tothe national grid.

 

Meanwhile, the officials and employees of the power plant are expressinghappiness at being able to supply electricity after overcoming variousobstacles.


News Link: Patuakhali Thermal Power Plant starts trial production

bottom of page