Ashuganj 450 MW (APSCL) DFG Power Plant (South)
- 2 days ago
- 5 min read
Current Status: Operation

Source: (TSK, 2023)
Ashuganj 450 MW Gas Power Plant (South), also known as Ashuganj South Thermal Power Plant, is a Combined Cycle (CC) power plant situated within Ashuganj Power Station Complex in Sonaram under Ashuganj Upazila in Brahmanbaria District of Bangladesh (Coordinates: 24.0432, 91.0149). It has been sponsored by Ashuganj Power Station Company Limited (APSCL), a State-owned Enterprise (SOE) under Bangladesh Power Development Board (BPDB), as a publicly owned Independent Power Producer (IPP) for 25 years. The sponsor declared its Commercial Operation Date (COD) on 22 July 2016 and, according to schedule, it is to retire on 21 July 2041.
Capacity
The installed (gross) and derated (net) capacity of the power plant was 382 MW and 359 MW respectively (APSCL, 2023a)
Context
Ashuganj Power Station Co Ltd (APSCL) functions as a power corporation engaged in the production and distribution of electricity. The company generates power through both thermal power plants and combined cycle power plants. Its operations involve seven generating units, comprising five steam turbine units, one gas engine, and one gas turbine, utilising natural gas as a source for power generation.
APSCL's notable project is the Ashuganj 450 MW Gas Power Plant (South), expected to commence commercial operations in late 2015. This project, a Combined Cycle Gas Turbine (CCGT) power plant, is developed and owned by Ashuganj Power Station. (PT, 2023). The project was commissioned on July 18, 2016 (APSCL, 2023a).
APSCL is approximately 75 km North East of Dhaka City. The Ashuganj 450 MW CCPP (South) power plant is situated adjacent to the existing Cycle Power Plant (450MW) within the APSCL premises on the bank of the River Meghna. It is noteworthy that the Combined Cycle Power Plant will be installed on APSCL's available land, eliminating the need for new land acquisition. This holds true for the Ashuganj 450 MW CCPP (South) as well. The plan is for all the unit(s) to be continuously powered by natural gas (MIGA, 2011).
Land Acquisition
As the power plant will be located within the APSCL's premises, there is no necessity for acquiring new land, thus eliminating any concerns related to resettlement. The initial land allocation for APSCL was 311 acres, a substantial portion of which has already been utilised. The designated site for the Ashuganj 450 MW CCPP (South) is at site no. 4, adjacent to the previously planned 450 MW CCPP. The total available area at site 4 is approximately 82,670 square meters, allowing for the accommodation of 2 (two) 450MW Power Plants configured in a 1:1:1 ratio (MIGA, 2011).
Finance
The plant is projected to be operational with an approximate cost of 37.92 billion BDT (DT, 2014).
Sponsor
The Ashuganj 450 MW Gas Power Plant (South) is funded by Ashuganj Power Station Company Limited (APSCL), a State-owned Enterprise (SOE) operating under the Bangladesh Power Development Board (BPDB), this project serves as a publicly owned Independent Power Producer (IPP) (APSCL, 2023b)
Contractors
Inelectra International and TSK Electronica y Electricidad were chosen to provide engineering procurement construction services for the gas-fired power project. Siemens was selected as the supplier of turbines for the project, furnishing one unit of the SGT5-4000F gas turbine and one unit of the SST-3000 steam turbine. Siemens also supplied the SGen5-2000H electric generator for the project. Additionally, the steam boiler for the project was provided by the John Cockerill Group (PT, 2023).
Fuel Supply
The power plant utilizes natural gas supplied via feeder lines from Titas Gas Transmission and Distribution Company Ltd (DT, 2014).
Power Generation
The plant has a total installed capacity of 382 MW. In the previous fiscal year, it generated 1,754 million kWh of electricity, resulting in sales revenue of BDT 10,315 million. The fuel cost for producing this electricity was BDT 2,904 million. Currently, the average tariff rate for this plant is BDT 2.004. The plant exhibits a plant factor of 53.24%, with an availability factor of 95.59% and a plant efficiency of 53.25%. Throughout the reporting period, the plant operated for a total of 5,912 hours. (APSCL, 2023b).
Environment
According to Section 12 of the Bangladesh Environment Protection Act 1995, Environmental Impact Assessment (EIA) is obligatory for any industry (MOLJPA 1995). The polluting industries, such as power plants, have to go through an Initial Environmental Examination (IEE) and EIA as directed in the Environmental Conservation Rules 1997 (superseded by ECR 2023) (MOEFCC 1997). As power projects are identified as having the potential for environmental impact, the Bangladesh Department of the Environment (DoE) has categorised them as being the “Red Category” of industrial processes. As such, an Initial Environmental Examination (IEE) and Environmental Impact Assessment (EIA) is required. Since the power plant will be within the APSCLs premises, no new requisition of land is required so there will be no question of resettlement.The total quantity of water withdrawal will be about 56.67m3/sec by all the units including the proposed 150 MW CCPP & 450 MW CCPP and the 450 MW CCPP South.This water will be discharged back to the river with a temperature rise of 7O degree Celcius which can be harmful for the aquatic organisms (MIGA, 2011).
Criticism
The power plant uses 29,000 cubic meters (28,478 tonnes) of water per hour from the Meghna River, which means it uses 683,472 tonnes of water per day and 249.47 million tonnes per year (ADB, 2016). The use of this amount of water can put aquatic species in danger. According to the environmental conservation rule 2023 the project falls in the “Red” indicating it as a potential harmful project for the environment (MOEFCC 2023).
References
ADB (2016). Environmental Impact Assessment: Power System Expansion and Efficiency Improvement Investment Program (Tranche 3). Asian Development Bank (ADB): May 2016.
APSCL (2023a). “Plant Status”. Ashuganj Power Station Company Ltd (APSCL): 18 November 2023.
APSCL (2023b). “Annual Report 2022-2023”. Ashuganj Power Station Company Ltd (APSCL): 12 October 2023.
DT (2014). “450MW Ashuganj plant to become operational next year”. Dhaka Tribune (DT): 30 September 2014.
MIGA (2011). “Detailed Feasibility Study And Environmental Impact Assessment Study For Ashuganj 450 Mw Combined Cycle Power Plant (South) At Ashuganj Existing Power Station Site”. Multilateral Investment Guarantee Agency (MIGA): June 20, 2011.
MOEFCC (1997). The Environmental Conservation Rules. Ministry of Environment, Forest and Climate Change (MOEFCC): 27 August 1997.
MOEFCC (2023). “The Environmental Conservation Rules”. Ministry of Environment, Forest and Climate Change (MOEFCC): 5 March 2023.
MOLJPA (1995). Bangladesh Environment Conservation Act 1995. Legislative and Parliamentary Affairs Division, Ministry of Law, Justice and Parliamentary Affairs (MOLJPA): 16 February 1995.
PT (2023). “Power plant profile: Ashuganj Combined Cycle Power Plant – South, Bangladesh”. Power Technology: 10 November 2023.
TSK (2023).”ASHUGANJ NORD AND SOUTH 2 x 450 MW CCGT”. TSK: 16 November 2023.
