Baraiyarhat 50 MW (SOSPL) Solar Power Plant
- 2 days ago
- 4 min read
Current Status: Pre-construction

Representational Picture (Source: Shutterstock/Jaroslava V)
Baraiyarhat 50 MW (SOSPL) Solar Power Plant, also called Baraiyarhat Solar PV Park, is a BPDB solar PV power plant to be situated at Baroyer Hat under Mirsharai Upazila in Chattogram District of Bangladesh (Location: 22.8926, 91.5339). The power plant is sponsored by Bangladesh Power Development Board (BPDB) as a private Independent Power Plant (IPP) under “no electricity, no payment” condition for 20 years. According to the latest schedule, the power plant will start its commercial operation in June 2025, and the retirement date of June 2045 will shift accordingly.
Capacity
The power plant's installed (gross) capacity will be 50 MW. The plant will have an installed DC capacity of approximately 68 MWp (megawatt-peak) to deliver 50 MWac (megawatt alternating current) to the grid. The 50 MW figure in the document refers to the AC output capacity (IPP, 2024)
Context
The state-run Bangladesh Power Development Board (BPDB) had invited proposals from private sector companies to construct four solar power plants in Chuadanga, Netrokona, Bhaluka, and Baraiyarhat, with a submission deadline of August 28, 2018 (FE, 2018).
A joint venture between a German and Bangladeshi consortium, IB Vogt had secured a tender to construct a 50-megawatt solar facility in Chittagong. The Cabinet Committee on Public Procurement of the Bangladeshi government granted approval for the contract to develop this solar project adjacent to the 132/33 kV substation at Baraiyarhat on 02 October, 2019. The solar developer, IB vogt GmbH from Germany, in collaboration with their local partner, AG Agro Industries Ltd, will be responsible for the construction, ownership, and operation of the plant. The government has entered into a 20-year agreement to purchase the electricity generated at the facility at a rate of USD $0.1094 per kilowatt-hour equivalent to BDT 8.75, per kilowatt hour on a condition of “no electricity, no payment” (PV Magazine, 2019; DT, 2019).
Bangladesh Power Development Board (BPDB) issued a Letter of Intent (LOI) on 15 December 2019 as a preliminary commitment to install the power plant (BPDB 2022). Currently, the project is in the permitting phase and is slated for development in a single construction phase (Power Technology, 2022). According to the LOI, the power plant's Commercial Operation Date (COD) is scheduled for 30 June 2023, but the respective Power Purchase Agreement is yet to be signed (BPDB 2022). Construction of the power plant is projected to start in 2023, with the project expected to become operational for commercial use in 2024 (Power Technology, 2022). But according to the latest BPDB progress report the power plant will start operation from June 2025 (BPDB, 2024)
Fuel Supply
Sunlight will be used as the fuel of the power plant.
Land Acquisition
The Baraiyarhat Solar PV Park is an upcoming ground-mounted solar power plant which will cover an area of 207 hectares (Power Technology, 2022). The original LOI (December 2019) was for a site in Sonagazi, Feni district; due to land acquisition complications, the site was relocated to Baraiyarhat in Mirsharai, Chittagong district (PV Magazine ,2024).
Finance
The anticipated expense for the project is approximately $49.8 million or BDT 547.306 crore (Power Technology, 2022). The total cumulative payment over the 20-year PPA period will be BDT 1,418.40 crore (Dhaka Tribune, 2019)
Sponsor
The consortium of IB Vogt GmbH and AG Agro Industries Ltd are jointly developing and currently share equal ownership, each holding a 50% stake in the project (Power Technology, 2022).
Contractors
IB vogt GmbH and AG Agro Industries Ltd, will be responsible for the construction of the project.
Power Generation
Expected Energy Generation will be 1 TWh (SREDA, 2023). The power produced equals the average consumption of more than 50,000 households and is estimated to save up to 70,000 metric tonnes of CO2 annually (IPP Journal, 2024)
Environment
According to Section 12 of the Bangladesh Environment Protection Act 1995, Environmental Impact Assessment (EIA) is obligatory for any industry (MOLJPA 1995). Polluting industries, such as power plants, must undergo an Initial Environmental Examination (IEE) and EIA as directed in the Environmental Conservation Rules 2017 (MOEFCC 1997). Ground-mounted solar panels offer numerous advantages over rooftop installations. They are positioned on the ground to optimize sun exposure, resulting in increased energy production. The flexibility in location means they can be placed in open areas with minimal shading, providing greater freedom in site selection. Ground-mounted solar panels offer environmental benefits by producing clean, renewable energy, reducing greenhouse gas emissions, and mitigating climate change. They also conserve land by utilizing non-arable or otherwise unused space. However, their installation can sometimes lead to habitat disruption, land-use conflicts, and potential visual impacts. Careful planning and consideration of ecological factors are essential to minimize these issues and maximize the positive environmental impact of ground-mounted solar projects.
According to the environmental conservation rule 2023 the project falls in the “Yellow” indicating it as a slightlyl harmful project for the environment (MOEFCC 2023).
Carbon Footprint
The power plant will reduce CO2 during its lifetime to 516 k tCO2 (SREDA, 2023).
Reference
BPDB (2022). “Power Sector Progress Report”. Bangladesh Power Development Board: 15 June 2022
BPDB (2024). “Power Sector Progress Report”. Bangladesh Power Development Board: 5 February 2024
DT (2019). “50MW grid-tied solar power plant to be set up in Chittagong”. Dhaka Tribune: 02 Oct 2019
FE (2018). “Govt plans to build four 50-MW solar plants”. The Financial Express: 20 July, 2018
MOEFCC (1997). ‘The Environmental Conservation Rules’. Ministry of Environment, Forest and Climate Change (MOEFCC): 27 August 1997.
MOEFCC (2023). “The Environmental Conservation Rules”. Ministry of Environment, Forest and Climate Change (MOEFCC): 5 March 2023.
MOLJPA (1995). ‘Bangladesh Environment Conservation Act 1995’. Legislative and Parliamentary Affairs Division, Ministry of Law, Justice and Parliamentary Affairs (MOLJPA): 16 February, 1995
Power Technology (2022). “Baraiyarhat Solar PV Park, Bangladesh”. Power Technology: 24 January, 2022.
PV Magazine (2019). “Ib vogt partnership wins bid for 50 MW solar plant in Bangladesh” pv magazine: 2 October, 2019
SREDA (2023). “National Database of Renewable Energy” Wayback Machine: accessed on 07 November, 2023
IPP, “PPA agreement signed for 50 MWac solar power in,” 05 August 2024
PV Magazine, “IB Vogt secures PPA for 50 MW solar power plant in Bangladesh,” 1 August 2024.
DT, “50MW grid-tied solar power plant to be set up in Chittagong,” Dhaka Tribune, 02 October 2019er 2023
